Workers from Houle Excavating of Little Falls remove pavement from Eighth Avenue S. on Tuesday night, part of Phase 3 of the Eighth and Ninth Avenue improvements near the middle school. Phase 3 began with street removals and will be followed by sanitary-sewer, water-main and storm- sewer installations. Completion for the entire project is set for Nov. 6, but the last 1.5 inches of bituminous pavement will not be placed until June.