The Sixth Avenue SE road construction project is underway in St. Stephen.

Here’s the work schedule:

May 18: Install traffic control, temporary mailboxes, erosion control and fencing

May 19-22: Reclaim road, grade and pack.

May 26-July 10: Road grading, subgrade excavation, sand correction and ditch work.

June 3-July 10: Install culverts.

July 10-Aug. 10: Finish grade road and gravel, erosion control.

Aug. 10-14: Pave road.

Aug. 17-Sept. 26: Clean up and complete project.